CONSTRUCTION
PROGRESS
Monthly reports from site, with photos from our construction partner. Completion is scheduled for Q4 2027.
42
%
Overall completion
Updated Sep 18, 2026
01
Excavation
Jul – Oct 2025
Complete
02
Structure
Nov 2025 – Jul 2026
Complete
03
Facade
Jun – Dec 2026
In progress
04
Interiors
Oct 2026 – Jul 2027
Upcoming
05
Handover
Q4 2027
Upcoming

Site camera · live
SITE UPDATES
Sep 18, 2026
Interiors
Model residence fit-out begins
Steel stud framing and MEP rough-in are under way on levels 2 and 3. The model residence opens for viewings in December.

Aug 2, 2026
Facade
Glazing reaches level 5
Floor-to-ceiling glazing is installed on the upper floors while the lower levels follow one floor behind.

Apr 12, 2026
Structure
Concrete frame tops out
The roof slab was poured on April 10, completing the seven-level frame two weeks ahead of programme.

Oct 28, 2025
Excavation
Foundations complete
Footings, column cages and the below-grade parking structure are finished and waterproofed.

MONTHLY UPDATES
Photos and milestones from site, once a month.